Results

Examples from current Jackhammer jobs. Client names are withheld. Each job is still active, so we show where it stands today.

Navy research facility interior build-out, Maryland (about $6.8M, federal 8(a) GC)

Problem: The notice to proceed hadn't been issued, and the contract's period-of-performance dates ended before the 430 calendar days the contract allows from NTP. The owner's paperwork also had gaps.
Jackhammer intervention: Our pre-start risk review (PRA/PUP) and the kickoff call flagged the date conflict before any work started. We agreed with the contractor that no work proceeds ahead of the NTP and that the schedule gets conformed with the contracting officer. We set a monthly check-in.
Where it stands: The NTP has been issued and the job is held at low risk after the November check-in. The contractor reports that owner-side funds-control payment routing is now working on its larger contract. We are still checking the NTP dates against the 430-day period.

Municipal PFAS water treatment plant, Pennsylvania (about $17.8M, municipal water GC)

Problem: Field work was on track, but the design engineer was returning submittals and only partly answering RFIs. It also rejected a one-pour clear well slab that would have saved about three weeks heading into winter concrete, with treatment tanks due in spring.
Jackhammer intervention: The monthly check-in pinned the risk on design review, not construction. The J/O made the one-pour slab the item to push, since it will soon be on the critical path. The contractor is keeping records of returned submittals, partial RFI answers and schedule impacts to protect its position on any delay claim.
Where it stands: The contractor is taking the slab RFI and the review issues to the owner's project manager.

Overseas U.S. embassy, 8(a) design-build (about $10.6M)

Problem: After award, bonding and kickoff, the government went silent for about two months: no notice to proceed and no design feedback. With work on hold and payment pending, the contractor faced termination risk.
Jackhammer intervention: The J/O gave the contractor a written escalation path (contracting officer, supervisor, agency ombudsman, SBA Procurement Center Representative) and kept the surety and bond agency informed without making the matter adversarial.
Where it stands: Escalation is underway, the surety and agency are aware, and a further route is held in reserve.

Municipal fleet services contract takeover, Texas (about $7.0M year-one bond)

Problem: The contractor took over a city contract after the previous contractor ran into financial trouble. The transition funding looked like guaranteed money but wasn't.
Jackhammer intervention: Our initial call documented the funding structure: a fixed-price base, a separate city-funded repair pool, and a one-time transition cap that is reimbursed only on invoiced costs. That kept the transition from being counted as revenue it wasn't.
Where it stands: The probation period runs through 11/30/2026, with no issues reported as of 10/23.